June 3, 1998 The Board of Supervisors adopts the Rio Linda and Elverta Community Plan, which identifies an urban development area in eastern Elverta.

February 1999

The Board of Supervisors appoints 11 citizens to the Elverta Specific Plan Citizens Advisory Committee (CAC).

 

March-May 1999

The CAC members and members of the public meet five times to help develop the land use plan.

 

Late 1999 through early 2000

Four CAC meetings held to formulate neighborhood design principles and guidelines and review Specific Plan text.

 

2000

Concept Land Use Plan Approved.

 

March 2003

Draft Environmental Impact Report (DEIR) released for public comment and review.

 

2004

The Policy Planning Commission conceptually approves the plan; County staff starts work to revise and re-circulate the Draft EIR.

 

2004

Affordable Housing Ordinance Approved.

 

2006

Revised DEIR released for public comment and review.

 

2006

Sacramento County Planning Commission approves the Elverta Specific Plan and forwards the Specific Plan and EIR to Board of Supervisors for action.

 

2007

Board of Supervisors approve Elverta Specific Plan unanimously.

 

Expected
2008-2009

Tentative maps and infrastructure design to begin.

 

Expected
2010

Major backbone infrastructure construction to begin.